97-H3 Double Story House in Wapda Town Lahore

This beautifully designed double story house in Wapda Town Lahore offers modern living with comfort and style. The layout includes spacious rooms, elegant interiors, and smart use of space for everyday convenience. High-quality construction, natural lighting, and premium finishing make it a perfect family home. It is designed to provide luxury, functionality, and a peaceful lifestyle in a prime location.

  • Spacious double story layout with modern design and comfortable living spaces
  • Premium construction quality with elegant interiors and natural lighting
  • Prime location in Wapda Town Lahore offering luxury and convenience
97-H3 Double Story House in Wapda Town Lahore​
Site Progress
45%
Phase: 1st Floor Brickwork
Design & Site Visuals
Front ElevationApproved Design
Site PhotosLatest — Apr 2026
Roof parapet work
Masonry work
Brick stacking
Interior filling
Interior filling
Interior filling
Construction Progress
Phase Timeline
Foundation & DPC
Jan 2026
Completed
Ground Floor Structure
Feb – Mar 2026
Completed
First Floor Brickwork
Apr 2026 – ongoing
completed
Roof Slab (First Floor)
Est. Jun 2026
completed
Plaster & Finishing
Est. Sep 2026
completed
Interior & Handover
Est. Dec 2026
Pending
Current Tasks
Foundation Concrete
Ground level
Done
Column Casting (GF)
8 columns complete
Done
Brick Masonry (1F)
100% done
done
Plumbing Rough-in
Ground floor
done
Electrical Conduit
GF walls
dong
Roof Slab Shuttering
First floor
Pending
External Plaster
Façade
Pending
Site Visit Notes
Field UpdatesChronological
17 Apr 2026
First floor brickwork in progress — approx 60% done. Plumbing rough-in for ground floor bathrooms underway. Electrical conduit placement ongoing in GF walls. Labour: 6 mistris + 4 helpers. On track.
Site Supervisor
05 Apr 2026
Ground floor lintel casting completed. Column casting for first floor begun. Material delivery: 5,000 bricks received and stacked. Water supply connected to site.
Site Engineer
20 Mar 2026
Ground floor slab casting done. Curing in progress. DPC applied on boundary walls.
Site Engineer
28 Jan 2026
Foundation work completed. PCC laid. Column footings cast as per structural drawings. Site levelling done.
Project Manager
Site photo

FAQs

The project is currently in the 1st Floor Brickwork phase, with approximately 60% of the brickwork complete. The ground floor structure has been finished, and as of April 2026, brickwork and plumbing rough-in are actively ongoing.

The estimated handover date is December 2026. Plaster and finishing work is scheduled for September 2026, followed by interior work and final handover by December 2026.

Yes, AQ Sons provides custom house plans along with flexible plan adjustment options. If you are not satisfied with an existing plan, your payment can be adjusted toward a fully customized design.

The 97-H3 project features premium quality construction, including high-grade materials, natural lighting, elegant interiors, and a modern double story layout with spacious, well-designed rooms for comfortable family living.

You can reach out directly via WhatsApp at +92 324 331 1311, or use the “For Detail Quotation” button on the project page to send a message and get a personalized quote.